Company News

Commissioning a Batching Plant in West Africa: A Service Diary

Home/ News/ Company News/ Article
Company News Editorial review by HAMAC

A field account of commissioning a 90 m3/h batching plant in West Africa: foundation checks, assembly, calibration and the first production run.

Arrival and foundation check

The plant arrived in containers after a long sea leg and a final stretch over poor roads. The first task on site was not assembly but verification: checking that the foundation matched the drawings, that anchor bolt positions were correct, and that the ground would carry the silos when full. Correcting a foundation after a plant is erected is expensive, so this check comes first.

In a hot, humid climate the electrical room also needed extra ventilation and a moisture barrier on the cable entries before any power was applied.

HAMAC concrete batching plant - 10
A batching plant installed and operating at an overseas project site

Assembly and calibration

Assembly followed the module sequence: main frame, mixing tower, conveyors, silos and screw conveyors, then the control cabin. Each load cell was calibrated with certified weights, and the batching accuracy was verified across the full range from small to full batches. Water and admixture dosing were checked separately, since slump problems on site are more often traced to water weighing than to aggregate weighing.

First production run and handover

The first mix was run at reduced load, then increased to full capacity while the team recorded cycle times and checked the discharge. Operators were trained on the control panel, on the daily cleaning routine and on the shutdown sequence for a power cut. A short list of site-specific checks was left with the customer, covering the points that change with local aggregate and weather.

StageDurationKey check
Foundation verification1 dayAnchor positions, load capacity
Mechanical assembly5-7 daysModule alignment, belt tracking
Electrical and calibration2-3 daysLoad cells, water dosing
Trial production1 dayCycle time, slump, accuracy
Operator training1 dayPanel use, cleaning, shutdown
HAMAC concrete batching plant - 8
HAMAC concrete batching plant - 8 supplied by HAMAC.
Need help applying this to your project?

Send your material type, target output and site conditions to HAMAC engineers. You will receive a practical equipment configuration and a clear quotation, normally within one working day.

Questions about this topic

How long does on-site commissioning take?

For a standard 90 m3/h plant, mechanical assembly takes about 5 to 7 days, followed by 2 to 3 days for electrical work and calibration and a day of trial production.

What foundation preparation is needed?

A level, reinforced concrete foundation matching HAMAC's anchor-bolt drawing, with adequate bearing capacity for full silos and a stable approach for delivery trucks.

Is operator training included?

Yes. Commissioning includes hands-on training on the control panel, daily maintenance and emergency shutdown, with a site-specific checklist left with the customer.

HAMAC Machinery Editorial Team

Written and reviewed by engineers and sales specialists who configure concrete batching plants, crushers, mixers and pumps for projects in more than 180 countries. Content is based on factory testing data and field feedback from delivered equipment.

Tags :
Keep reading

Related articles

All news

Turn this knowledge into a working plant

HAMAC engineers translate your output target, material and site layout into a concrete or aggregate production configuration.